What is the Deadline for Filing a Lien on a Commercial Project?

lovein-ribman-logo

TEXAS CONSTRUCTION LAWYERS
Call (888) 368-2483

The lien affidavit must be filed with the County Clerk’s Office in the county where the property is located by no later than the 15th day of the fourth month from when you last worked at the project, excluding punch work and warranty work.

NOTE: The deadline to file a Lien is not extended if the 15th falls on a Saturday, Sunday, or legal holiday.  If your deadline falls on one of these days, file the Lien Affidavit on the preceding business day. The Lien Affidavit must actually be filed, not simply placed in the mail or waiting at the clerk’s office to be filed.

LIEN FILING CALENDAR

In the left-hand column, locate the month that you provided labor and/or materials to the project and for which you have not yet been paid. In the corresponding right-hand column, is the deadline for filing a lien for money owed for the labor and/or materials provided to the project in that month.

MONTH OF “ACCURAL OF INDEBTEDNESS” FILE LIEN ON OR BEFORE DATE
January May 15
February June 15
March July 15
April August 15
May September 15
June October 15
July November 15
August December 15
September January 15
October February 15
November March 15
December April 15